Back River Wastewater Methane Cogeneration Project

Back River_pic 2Program Leader helped the author lead three corporate divisions and eight subcontractors to design, construct, startup, and close-out a $16 million 3 mW cogeneration and energy savings project.

The above facility used cryogenic gas cooling to purify the fuel: digester gas from wastewater treatment.  The project was a finalist in an ACEC statewide Competition.

The day that Program Leader showed that all punch list items were complete, the client signed the Physical Completion notice.